News & Headlines

August 2003 Cleaner Magazine Tough Job
Happy As a Clam


A utility in the Twin Cities finds that older technology
works best to remove tons of sand and
gravel from a sanitary sewer.

Sixty-three years of debris had accumulated in the main sanitary sewer in St. Paul, Minn. Dug under a limestone stratum in 1937, the 6-foot tall by 2-foot wide semi-oval tunnel runs five miles through the city's west end.

During the winter of 2000, the St. Paul Sewer Division (SPSD) began cleaning the entire sewer by removing the two feet of accumulated sand and gravel with shovels and wheelbarrows. Crews labored 100 feet below ground in three feet of water flowing at 700 to 900 gallons per minute. "Our guys worked hard, and were getting badly beat up," says Jim Sirian, the shop's maintenance foreman. "It also didn't make sense to have a $250,000 vacuum truck sucking debris out of a wheelbarrow."


The next winter, after paying $100,000 to a contractor to clean 400 feet of line using two cranes and a bucket, the department again looked in-house. Sirian knew that new machinery would allow city personnel to do the jog, and he suggested calling Jeff Schultz of Sewer Equipment Company of America, based in Glenview, Ill. The two had met at the Minnesota Onsite Sewage Treatment Contractor's Association's annual conference in January.

The amount of water in the tunnel made jetting impractical, so Schultz recommended an old-fashioned solution--clamshell bucket machines--to conquer a 21st century problem and save the department millions of dollars.

Running Deep
St. Paul sits on a bluff overlooking the Mississippi River, and its sewers and storm tunnels run 60 to 100 feet deep, depending upon whether the manhole is set on a hill or in a dale.

"When the pull-in machine and truck loader arrived in the spring of 2002, they paid us back in the first two weeks," says Sirian. Throughout the summer, a two-man crew extracted two to four cubic yards of debris a day using an 18-inch bucket.

"That doesn't sound like much," continues Sirian, "until you realize that each pull averages 1,000 to 2,000 feet between manholes, then comes up 100 feet. This is a lot of work."

In one 1,700-foot section on the outskirts of St. Paul, at least two feet of sand and gravel with the consistency of fresh asphalt lay on the bottom. The tunnel is less than 100 feet deep here because the manholes are in a hollow.

Work's A Drag
After parking the pull-in machine over one manhole and truck loader over the next consecutive manhole, each operator (one per machine) sets the start and stop meter on his drag line. The distance between manholes determines the drag line's length, which is 1,700 feet for this section.

The clam bucket is in the middle of these two drag lines. Tension on the hoist cables when raising the bucket tells the men if they dragged far enough to fill it. By the time the bucket arrives at the surface, all the water in the debris has drained out. The bucket then travels up a ramp on the truck loader and dumps into a 3-cubic-yard garbage container. When this is full, the crew radios for one of the department's four Vactor trucks to transport the debris and dump it into a 12-foot-diameter interceptor pipe near downtown St. Paul.

A 100 mgd flow rate carries the sand and gravel two miles to the city's wastewater treatment plant, where it passes through a grit chamber and settling tanks before being mechanically raked and pumped off the bottom. It is dewatered, then hauled to a landfill.

OSHA Compliance
"It's a big process," says Sirian. "We're moving tons of sand and gravel. Right now, we're halfway through cleaning the entire sewer. It's impossible to estimate when we'll be done, because work is interrupted whenever our two-man crew is needed elsewhere for priority projects or emergencies."

Pulling a total of 15 to 20 miles a day for weeks and months is causing parts on the equipment to wear out. If the bucket jumps the rollers or a chain snaps, it usually happens in the tunnel. "We follow OSHA's confined space regulations," says Sirian. "Our guys radio for two more, then wait for them to serve as attendant and entry supervisor. Before going down, they meter the air in the manhole. They each have two air monitors with them and carry 15-minute air packs." The SPSD has had no work-related injuries on this job.

Since the hydraulic bucket machines went into operation, Sirian estimates they have saved the department $2 million. A second set has been ordered.

Reprinted with permission from Cleaner, (August) 2003 / COLE Publishing Inc. / 800-257-7222 / www.cleaner.com

»Back to the main news page

All inquiries and information requests can be sent to:
sales@sewerequipment.com
 
2111 CHESTNUT AVE. # 270 • GLENVIEW, ILLINOIS 60025 • U.S.A.: 1-847-729-3316 FAX: 1-847-729-3547
© 2008 Sewer Equipment Company Of America ®, All Rights Reserved.
All specifications subject to change without written notice. See your local dealer for details.